Be glad. Worst is when managers estimate themselves. Be pessimistic, don't count happy flow only. Count also meetings and other organizational slowdowns into e
by watwut 9y ago
Be glad. Worst is when managers estimate themselves.
Be pessimistic, don't count happy flow only. Count also meetings and other organizational slowdowns into estimation. It can be anything between 30% to 200% of needed time depending on what politics on your company is.
Break it down, and guess shortest time possible, longset time possible and them most likely time for each task. Then do (min+max+4×likely)/6 and sum them. The result will look intuitively too long, but resist temptation to shorten it.
Then resist pressure to make it smaller. If they want it faster, keep calm and ask them whether take out this or that feature. The only way to make it faster is by cutting features.
- valuearb 9y agoNo time estimate should ever be made by anyone not responsible for implementing it.