At our company we didn’t estimate entire projects, but separated tasks until it was 3-5 hours piece of work that everyone agreed “it’s realistic, I can do it”.
by wruza 9y ago
At our company we didn’t estimate entire projects, but separated tasks until it was 3-5 hours piece of work that everyone agreed “it’s realistic, I can do it”. The big time then simply summed up with 30% buffer for delays. Since our customers mostly paid for hours, it was also a good base price builder.
Big projects can suffer from this because little architecture is involved (and we worked on already existing systems). Otoh, I’ve seen no big local project that wasn’t an architectural mess once it hit a deadline hard. It is better to not have one than to have a set of rules that you must obey, while other parts of system don’t even care of or contradict these.
Personally I don’t believe this “I’ll get back to you with an estimate” thing. It is just first iteration where you go relax and try to formulate at least 5-10 questions that you think you should ask foremost to start building an estimate. If you come back with an answer instead, then it is still wrong, maybe even worse than random, since you estimated a different thing. For us, estimates and requirements always moved, as they were functions of delays and business priorities that change unpredictably. I didn’t like to deliver the entirety on a deadline because my job was to support that for years, not throw a bill at them and run, as all integrators did.
Maybe, maybe these SE-users are speaking about coding phase, when all “business analysis” was done perfectly. But ime it is you coder who collects all the knowledge, because no one can. Or it is you who is non-coding analyst who must estimate, because non-analytic coders don’t have a clue what a big picture is.