> May I ask what could possibly take 12 weeks worth of work before having anything useful? 12 person weeks is a tiny amount of effort. > but in the first spri
by sheepmullet 9y ago
> May I ask what could possibly take 12 weeks worth of work before having anything useful?
12 person weeks is a tiny amount of effort.
> but in the first sprint you can release the component to tokenize strings, for example.
Ah I see - You just have to redefine what useful means :P.
If your customer needs a search engine then having a string tokenizer is not useful at all.
You don't run a project this way to improve individual developer productivity. You run it this way to reduce infrastructure and project risk.
Often using Scrum practices is a good tradeoff - the problem is the messaging. The truth is we are trading off developer productivity and growth in order to lower overall risk and make the software process more predictable.