Lack of testing; ideally you throw a switch once a month or so to make sure the UPSes work and the generators power on, but I can imagine it's something you'd r
by Cthulhu_ 9y ago
Lack of testing; ideally you throw a switch once a month or so to make sure the UPSes work and the generators power on, but I can imagine it's something you'd rather not do, if it doesn't work you've just intentionally borked things for your customers. Still, it is something that datacenters should do, do it a few times before you have any customers, keep doing it. Maybe offer a discount (if it's a new datacenter for an existing provider, like AWS or whatever) for the first couple months, indicating that emergency power has not yet been tested properly.
There's tooling available and running at some of the larger companies (like Netflix) called Chaos Monkey, which triggers random outages constantly to determine if the system is resilient and self-healing.
- smoyer 9y agoWe always had our generators cycle on once a week for 20 minutes or so without assuming load. You don't want the (in our case propane) engines sitting too long without being run.