The stuff about the bi-directional meter is warblegarble. What the requirement is talking about is operating a grid tie system before FPL upgrades the meter to
by maxerickson 9y ago
The stuff about the bi-directional meter is warblegarble.
What the requirement is talking about is operating a grid tie system before FPL upgrades the meter to one that measures in both directions in a way that meets their requirements. This is a sensible requirement, not a ginned up excuse.
(all the quotes are coming from a linked grid interconnection guideline https://www.fpl.com/clean-energy/net-metering/guidelines.html https://www.fpl.com/clean-energy/net-metering/guidelines.htm... )
I wonder if there is actually any legal requirement to have a grid interconnection. The article isn't real convincing.