Heavy expensive machinery on private projects tends to be iddle too and planning of machinery is what I was responding to. The construction site stops idle ent
by watwut 9y ago
Heavy expensive machinery on private projects tends to be iddle too and planning of machinery is what I was responding to.
The construction site stops idle entirely for months issue is often that fund used to pay for construction dried out or got redirected. Or that there are legal issues to be sorted - that one happen with private companies too.
Additional work "needs to be put out to bid instead of using the on site contractor" because otherwise contractors would underestimate prices and then charge a lot more or predictable "excess". There does not even need to be bad intention originally, such system would simply favor contractor who makes bad estimates "naturally".