> I think the secret might be just to ensure that work starts and finishes on a project as soon as possible, that both people and expensive equipment have work
by watwut 9y ago
> I think the secret might be just to ensure that work starts and finishes on a project as soon as possible, that both people and expensive equipment have work ready for them so they can keep busy constantly until the job is finished.
You gotta have buffers for bad weather, malfunctions, changing stuff when it turns out some worker did bad job, yadda yadda yadda. Otherwise your construction ends the same way as any software project with tight schedule - buggy, low quality and over budget due to subsequent three years of fixing.
Transporting large machines from place to place is expensive and time consuming, so if you need to lift something heavy once a day, you have to keep them where they are. The company that provides those machines also needs buffers between jobs - otherwise two days of heavy rain on one site would delay start of work on another site (which usually means contractual fines).
I don't mean to say that the construction you look at is the most effective possible, certainly not. But sometimes there are reasons.
> And maybe it'd help if people were cross-trained to do multiple trades, so that after one task is completed, they could immediately go work on another.
I would agree, but finding reliable high quality worker is hard enough. Finding one who is reliable high quality and knows two trades might be even harder.
- alacombe 9y ago> You gotta have buffers for bad weather, malfunctions, changing stuff when it turns out some worker did bad job, yadda yadda yadda Private projects face the same issues, but do not necessarily stop for these reason. After all, time is money, and a dead construction site not running cost the owner money.
- watwut 9y agoHeavy expensive machinery on private projects tends to be iddle too and planning of machinery is what I was responding to. The construction site stops idle entirely for months issue is often that fund used to pay for construction dried out or got redirected. Or that there are legal issues to be sorted - that one happen with private companies too. Additional work "needs to be put out to bid instead of using the on site contractor" because otherwise contractors would underestimate prices and then charge a lot more or predictable "excess". There does not even need to be bad intention originally, such system would simply favor contractor who makes bad estimates "naturally".