[edit] Reporting on a high level ("yesterday - analytics, today - analytics") is fine only up to a point. This statement only works when team members are 1) mat
by jakubp 9y ago
[edit] Reporting on a high level ("yesterday - analytics, today - analytics") is fine only up to a point. This statement only works when team members are 1) mature (to admit problems) and 2) very self-aware (to accurately assess if they are making progress).
Unfortunately, huge percentage of people in software houses I've seen are young and therefore both immature and not very self-aware. They have a hard time recognizing the upcoming issues, and will not admit they made a mistake or are unsure if they can succeed on time.
The results? People claim they are on track, then they fail, goals aren't achieved. This happens over and over.
Eventually Project Manager or senior developers start probing more and more, dividing the work more, creating smaller (shorter) tasks to cater for less independent employees, adding short iterations, daily checkups and ...
Wait, we created "agile". Haven't we?
Overreport and micromanage to deal with issues.
- humanrebar 9y agoThis is why I regularly advise new hires, both senior and right out of college, that communicating when you're blocked or stuck is not optional. The quickest way to get me to recommend a performance improvement plan isn't if you can't hack it on a particular task, it's if you aren't clear that you don't have what you need (voodoo to get tools working, training, experience) to get the job done. Being stuck and not speaking up is a cardinal sin in knowledge work.