They already do this without any gov intervention. The local steel recycling plant only operates when power is cheap. While they do need some advance notice to
by extrapickles 9y ago
They already do this without any gov intervention. The local steel recycling plant only operates when power is cheap. While they do need some advance notice to make sure they have enough people to run, they probably can get a good enough idea from a weather forecast (power here is mostly hydro with a dollop of wind and fossil).
Some processes are better fits than others. If you have 2-5x extra capacity that is sold cheap on sunny days, someone will figure out how to use it.
- TheSpiceIsLife 9y agoDo we have any numbers on what it means that they run only when the power is cheap? Does that mean they can operate in 4hr windows? Or do they run have to run the furnace for a minimum period? A large quantity of steel takes a large amount of energy to melt.
- maxerickson 9y agoInteresting question. Brief research says the cycle time is ~1 hour (or less): http://www.steel.org/making-steel/how-its-made/processes/processes-info/electric-arc-furnace-steelmaking.aspx http://www.steel.org/making-steel/how-its-made/processes/pro... It could also be a plant for shredding scrap, where I guess it wouldn't be a time issue so much (and if it doesn't have the material inflows to run full time, timing cheap power would make sense).
- TheSpiceIsLife 9y agoThanks for the link, looks pretty detailed. I work in steel fabrication, so it'll make interesting reading for me.