As a PM, of course, I know this padding is happening and generally will add my own: You know in your mind it will take you 3 days You give me, your PM, an est
by ryandrake 10y ago
As a PM, of course, I know this padding is happening and generally will add my own:
You know in your mind it will take you 3 days
You give me, your PM, an estimate of 2 weeks
I report up the chain that it will take a month
When it's all said and done, you end up getting it done in a month by the skin of your teeth :-)
- 6t6t6t6 10y agoBut my point is that if there is a relation of trust between the PM and the developers, padding is unnecessary. I had PMs to who I could give optimistic estimations and risks. That way, the PM could plan the different scenarios (like extra features in case we had spare time). Other PMs, the ones who converted estimations into deadlines, got lots of padding. And the problem of adding padding is that it is time lost, because a developer who adds padding cannot tell that they finished earlier.