The following NREL page provides information on Ouarzazate (Phase I), a concentrating solar power (CSP) project, with data organized by background, participants
by georgecmu 10y ago
The following NREL page provides information on Ouarzazate (Phase I), a concentrating solar power (CSP) project, with data organized by background, participants, and power plant configuration:
http://www.nrel.gov/csp/solarpaces/project_detail.cfm/projectID=270 http://www.nrel.gov/csp/solarpaces/project_detail.cfm/projec...
Solar Resource: 2,635 kWh/m2/yr
Break Ground: May 10, 2013
Start Production: December 1, 2015
Cost (approx): 1,042 € million
PPA/Tariff Date: November 19, 2012
PPA/Tariff Rate: 1.62 Dirhams per kWh
PPA/Tariff Period: 25 years
PPA/Tariff Information: US$ cents 18.9 per kWh
Project Type: Commercial