> So lets assume we are going nuc crazy and are ordering a 10 GW of plants. Can any nuclear power plant builder actually build this within 5 years? 10 years? C
by sanxiyn 10y ago
> So lets assume we are going nuc crazy and are ordering a 10 GW of plants. Can any nuclear power plant builder actually build this within 5 years? 10 years?
China can. As a matter of fact, China connected 20 GW (20863 MW to be exact) capacity to grid within 5 years, from 2012 to 2016.
Check for yourself using IAEA PRIS(Power Reactor Information System): https://www.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN https://www.iaea.org/PRIS/CountryStatistics/CountryDetails.a...