1) pole rights matter. In San Francisco, att also owns the poles and does everything they can to prevent other people from using them. I would tell installs tha
by josh2600 10y ago
1) pole rights matter. In San Francisco, att also owns the poles and does everything they can to prevent other people from using them. I would tell installs that it would be 30 days from the day we got permitted until the circuit was installed, but that despite there being a 30-day limit on replies for pole permits, many times att would wait 180 days before issuing access permits. It was honestly a joke around the office.
2) many cities do not have above-ground power and fewer still have above-ground telco without power. I have not researched this extensively so I am not sure if google picked places with poles specifically, but that would be a smart move. That being said, imagining att would let them use the poles was not really reasonable.