The vast majority of the time, we’d overestimate the amount of work we could do. Granted, we did get more disciplined about estimating and we eventually fell in
by vannevar 10y ago
The vast majority of the time, we’d overestimate the amount of work we could do. Granted, we did get more disciplined about estimating and we eventually fell into a cadence. But still, we were off every time.
I've been on a number of agile teams in several different companies, and I've never been on a team that missed their target every single time.
I remember once we planned a sprint that included only about 25% of what we actually thought we could handle, and we barely made it.
Sounds like they finally locked in on the right velocity. Probably should've stuck with it.