At a previous job, we had serious development bandwidth issues. The company was trying to solve that by hiring more developers, and all it was doing was making
by bunderbunder 10y ago
At a previous job, we had serious development bandwidth issues. The company was trying to solve that by hiring more developers, and all it was doing was making things worse.
The root cause of the development bandwidth problem was that we wasted vast amounts of time and energy on building misfeatures. And we built so many misfeatures because we had way too much development capacity in relation to our product planning capacity. So the BAs didn't have enough time to fully develop ideas before sending them to engineering, and were instead stuck throwing things over the wall when they were still half baked. All these half-baked ideas took time to build, and then they took time to fix after they bombed on the market, and they slowed everything else down since every new feature is something you have to ensure still works when you make a change in that part of the software. Day in, day out, we were taking on technical debt to cover our design debt bills.
So then we tried Agile, and man oh man did that make things worse. 'Cuz now instead of just lobbing things over the wall, the BAs had to be actively involved in every sprint. There goes any opportunity to sit down and concentrate, because now you've got a nattering horde of 20 developers all trying to get clarification on last week's decisions, which leaves less time to make this week's decisions, which means next sprint things will be even more sketchy and ill-defined.
The correct solution would have been to hire more business analysts, and they key thing we needed from those business analysts wasn't instructions on what to build. It was instructions on what _not_ to build.
- amag 10y ago> The company was trying to solve that by hiring more developers, and all it was doing was making things worse. You don't mess with Brook's law!
- knightofmars 10y agoI second this. Additionally, get a grip on your queues! I have yet to find a better text on how to properly manage software projects than, "The Principles of Product Development Flow: Second Generation Lean Product Development"[0]. [0] https://www.amazon.com/Principles-Product-Development-Flow-Generation/dp/1935401009 https://www.amazon.com/Principles-Product-Development-Flow-G...
- deleted 10y ago[deleted]
- hinkley 10y agoI know I've seen this pattern in person, but something about the way you wrote it makes me want to go back and think about some of my other projects before I could identify that was the problem. I know one project in particular we did a release about every 7 months. Every release cycle they estimated 2 weeks for requirements, every cycle took a month, and yet the next cycle you'd see a 2 week estimate on the roadmap. As for switching to Agile, I know some people would tell you that Kanban would identify this problem for you by around week 8. Did you guys ever try having development liaisons help them draft requirements that were precise from an engineering perspective? Sometimes that initial meeting works better when there are only three people in the room, instead of a bunch of exasperated people being condescending to you again while you're trying to do a good job. adjusts collar nervously I'm uh... asking for a friend.
- knightofmars 10y ago"...precise from an engineering perspective?", this (in my experience[0]) doesn't work. Because requirements are messy and always change. As they say, " No plan survives contact with the enemy." and "No requirement survives contact with implementation." The reality is that you need to come up with a timeline that accounts for this problem (say 8 weeks) and only scope the release to fill 50% (4 weeks). An 8 week release cycle may even be on the long end of a release cycle. Why 50% of a release's entire timeline? Because you're going to have overruns, errors, re-dos, and any number of random unplanned elements creep into the scope of your release. And the reality (I may get blasted for this blasphemy) scope creep is fine. As long as it pertains to the originally scoped requirements and is clearly adding value. "A delayed game is eventually good, but a rushed game is forever bad.", Shigeru Miyamoto. The important part of that quote is "delayed", you still need to make sure you release otherwise you're just spinning and wasting company time and money. And whatever you do, don't try and "fill in weeks". If the release is ahead of schedule, let it be. Let it finish weeks early if it has to. Then, rinse and repeat. Admittedly this type of release process can be hard to sell because there's usually a negative emotional response to the idea of only scoping 50% of the total allowed release cycle and that somehow the other 50% is waste. It isn't, it's there to guarantee that the items scoped initially actually get done on time. That way QA can get to them in a reasonable amount of time, give feedback, and (during the second half of the release) engineering can fix the issues raised by QA. Business development can also rest comfortably knowing that the features scoped into the first half of the release are actually going to come out on time. I know it sounds like "You're just adding slack." But it's intended to be more than that. If you see teams attempting to squeeze more items into the 50% release you know there's a prioritization problem within those teams. Which can be remedied by either: 1) reducing the overall size of the release cycle further (eg 8 to 4 weeks with 2 weeks as the 50% mark) to provide more flexibility into what goes into the product in a shorter time frame. 2) Helping those teams clarify what the high-level product direction and priorities should be. Hopefully this 15 minute rambling comment is valuable to you. If not, I apologize. [0]The mistake I made and the advice I can personally give, don't focus on up front high-accuracy estimates and designs. Come up with a reasonable design, your best guess estimate, and then implement as furiously as possible (coding best practices should still be enforced). You'll know much earlier in the release cycle what the real timeline for your feature will be than if you'd tried to spend all that time up front.