Someone taught me, years ago, some technique (don't remember the name) where you would move all the tasks to begin in the last possible day. Then, study the cr
by woliveirajr 10y ago
Someone taught me, years ago, some technique (don't remember the name) where you would move all the tasks to begin in the last possible day.
Then, study the critical path to exclude all those "extra fat" that everybody includes in each task, assuring that the critical path is really critical, without hiding days/hours that would lead to procrastination in the critical path. Save it to an "emergency buffer".
Review if something else became the critical path. Repeat until stability arises.
Now, manage it, use your buffer when required, always take care if something else becomes the critical path (as everything will begin in the last possible time).
And, even if something becomes critical path and takes more time than required,
you have some buffer...
- asplake 10y agoReminds me of Goldratt's Critical Chain - he of Theory of Constraints (TOC), The Goal, etc
- kesor 10y agoReminds? It is a direct quote of Critical Chain, see #37
- scrame 10y agoUntil you drown in technical debt.
- woliveirajr 10y agoYes... If the PM don't let some time to that tech research about the "good enough" solution, the long run can be ugly.