I've seen the "you're doing it wrong" argument so many times (I applied it myself a few times). Scrum is complex and not always possible to follow exactly, so
by bhaak 10y ago
I've seen the "you're doing it wrong" argument so many times (I applied it myself a few times).
Scrum is complex and not always possible to follow exactly, so this is to be expected but it makes me wonder, how many successful projects are out there that are following the true Scrum methodology?
My guess is that it's a few more than the classic waterfall but I still seem to see far more failure than success stories.
- blub 10y agoThe very idea of a one-size-fits-all process is unrealistic IMO. Something will always be customised in practice. Regarding success stories, it might be that process doesn't play such a critical role as long as solid engineering techniques are used and the team is competent.
- bhaak 10y agoIf your team is competent and solid engineering techniques are being used, you already have a well working process. Forcing any methodology on this will likely result in a deterioration. All those methodologies are for the less stellar programming teams, to get consistent results from those (also to a lesser degree to make good and bad programmers work well along each other). Because you can't always get the best programmers. If Scrum would only work well with good programmers, it would be next to useless.
- xorblurb 10y agoSuccessful big waterfall engineering projects where waterfall is actually applied exist. Want to construct a bridge or a rocket, design a microprocessor? You are not going to do that with "stories". It remains to be seen if big Scrum engineering projects where Scrum is actually applied even exist. I can't even think about one on the top of my head. I'm not even sure Scrum is that well defined for us to be able to judge if is correctly applied or not. And it's yet another story to judge if they are successful or not. In the end it does not matter much. The theoretical vision that nobody ever uses has almost no interest if you are concerned with real world efficiencies.
- dragonwriter 10y ago> Successful big waterfall engineering projects where waterfall is actually applied exist. You are engaging in equivocation. > Want to construct a bridge or a rocket, design a microprocessor? You are not going to do that with "stories". Nor are you going to use the software development methodology described as the waterfall method (you may use a physical engineering methodology that was among the inspirations for that software development methodology, but those are distinctly different things, with different specific practices, and different domains.) > I'm not even sure Scrum is that well defined for us to be able to judge if is correctly applied or not. Scrum is exquisitely well-defined, both as to what it involves, what it specifically excludes, and what it is neutral to, in the Scrum Guide. (There's lots of confusion between Agile, a broad approach which is not a specific methodology, and Scrum, a very-specifically-defined -- though by itself fairly incomplete, in that any implementation of Scrum needs lots of decisions on the things to which Scrum is neutral -- methodology.)
- xorblurb 10y agoOk I maybe went a little far for the bridge, but today a microprocessor is way more similar to software than it is to a bridge (at least in some of the design phase, but then now even in some maintenance phases). And a modern rocket also contains tons of software. And waterfall is similar enough to (at least non-software -- but in my thesis also software) engineering to even consider a direct equivalent for the bridge. Only, quite like a description of a method is often not enough to see how it is properly used, the mythical "waterfall" where a phase begins after the other one, strictly, never happens, and there are all kind of loopbacks -- even for the bridge -- and obviously if you try to remove loopback things will get fucked-up, but why would you try to do that? Now in real world conversations, waterfall is used to designate software being developed with proper general engineering practices. Scrum origin is partly in manufacturing. Now there are some common points between some aspects of software dev and manufacturing, especially more so if the software being developed can be iterated very quickly (but very few if it's not the case), but at least in the real world (and maybe even in the theory) Scrum is what is also actually mainly used to interact with other stakeholders. And given how the communication is performed, and its content, that might be better than complete chaos when nobody is actually able to do the work they are supposed to do (PM being limited to having vague ideas, lack of a truly competent tech lead doing actual tech lead work, lack of vision by management, and so over) and only very vague general ideas of what should do the software -- or more generally the whole product -- are ever emitted. As soon as "serious" stuff starts to be involved, you need real boring engineering, with functional analysis, requirement engineering, modeling, systematic testing or even partial proofs, etc. And you need to have it structuring communication between teams, and day to day work. And then, I don't expect Scrum or anything Agile in such a context adding any kind of value. Now the theory of Agile and Scrum has evolved because of criticisms to a point where we are told that it actually do not cover the things that matter. That is bullshit retro-justification, now that the world is fucked up trying to make sense how to use that. Here is the Agile manifesto: > We are uncovering better ways of developing software by doing it and helping others do it. Through this work we have come to value: > Individuals and interactions over processes and tools > Working software over comprehensive documentation > Customer collaboration over contract negotiation > Responding to change over following a plan > That is, while there is value in the items on the right, we value the items on the left more. Engineering is mainly about "processes and tools", of course "individuals and interactions" are also needed, but there is no need to oppose them (although I am not sure what is the point of "individuals" here; the authors might as well said "oh and by the way be nice") "comprehensive documentation" is critical in all kind of domains, and now that software is everywhere it just makes no sense to declare your "preference" of "working software" above "comprehensive documentation". It is, again, even dangerous to oppose them. Customer collaboration over contract negotiation; again, highly dependent on the field and specific project if this is something where it makes sense to even have a "preference" or not. "Following a plan" is what you do about how you organize your work when you use Scrum. There is no problem in studying the impact of a change any time if proper engineering practices are used. Obviously, the cost can vary depending on various factors. My conclusion about Agile and Scrum, is that if you prefer all of that (4 Agile preferences, and the Scrum theater), you should seek projects that are suitable for the Agile preferences, and so poorly defined that Scrum is a plus. On my side, I'm just not seeking to work on chaotic projects -- on the contrary I try to bring logical and more systematic practice where I feel that chaos reigns -- and I'm neutral about Agile preferences, I prefer to choose projects on other criteria (mostly; intrinsical interest)