But that is exactly how I normally respond to estimate requests. "I have 70% confidence it will take between X and Y hours." That's a huge difference from sayin
by HeyLaughingBoy 10y ago
But that is exactly how I normally respond to estimate requests. "I have 70% confidence it will take between X and Y hours." That's a huge difference from saying "I have no fucking clue." If I say I think something can be done in 6 weeks and I'm 70% sure, Management now can weigh the risk that I'm wrong against the benefit.
Most software projects in a given company really don't vary all that much, so it often is like installing a WP blog. Since most companies do only minor variations of the same thing, you have pretty good history of how long the last variation took.
I can think of my last job for example. We built extremely complex medical devices, but yet we could say: software for this product will take us 4 years from concept to getting it on the market and we'd be accurate within a couple of months. It takes work and planning and sitting down and literally thinking of every major task along the way and trying to estimate how long it will take. Estimation of that sort is expensive and you have to have a good reason to take the time to do it. You also have to keep re-estimating as time goes on. Schedules aren't fixed in stone if they are to mean anything. Have to make a market window and you're running late? Well if your estimates mean anything, then features have to be removed or you ain't gonna make it!
I do agree with the management comment. You need good management that understands what they're doing. Management that understands if they change features, there is a cost. But it's up to developers to continue to make this clear to them.
- ScottBurson 10y ago> Estimation of that sort is expensive and you have to have a good reason to take the time to do it. Just wanted to emphasize this sentence. Good estimates take time and cost money -- time and money that aren't necessarily worth spending. In many cases you're better off living with order-of-magnitude estimates and spending most of your time doing the actual work -- depending on the nature of the business, of course.