I would argue that point-based estimation is just as inaccurate as time-based estimation in that it only serves as a proxy for effort, which is done over time.
by dastbe 11y ago
I would argue that point-based estimation is just as inaccurate as time-based estimation in that it only serves as a proxy for effort, which is done over time. Point systems (and time systems) have two big issues
* You're throwing away all your data points when you condense a story down to a single point. Systems exist to try and avoid things like anchoring bias, but you just throw it away.
* You imply uncertainty exists about the task duration, but don't try and measure how uncertain you are.
Using Monte Carlo simulation here can really help address these two issues.