The seawall was shorter than it should have been, that is a planning and design failure, not just ignoring warning signs. There also doesn't seem to have been
by maxerickson 11y ago
The seawall was shorter than it should have been, that is a planning and design failure, not just ignoring warning signs.
There also doesn't seem to have been any planning for a situation where the seawall failed (the inundation rendered the on site backup power inoperative). Adding a second layer of protection to such an important system would not be particularly aggressive.