This is very true. The best way I have found to combat it is by splitting up the tasks into many smaller pieces. If you have a task that is scheduled to take
by mikekchar 11y ago
This is very true. The best way I have found to combat it is by splitting up the tasks into many smaller pieces. If you have a task that is scheduled to take a month, then it can easily go out to 10 months in the worst case. If you have a task that is scheduled to take a day, it can easily go out to 10 days in the worst case. This allows you to make corrections to your schedule.
There are 2 other important issues. First, you need to update your schedule based on the amount of time tasks are actually taking. If you only have 10 tasks (each taking a month), the error bars can be quite significant. But if you have 200 tasks (each taking a day), the mean completion time will have quite small error bars. So if you keep a rolling average (say over the last 30 tasks), you can have a fairly good estimate for completion time (agile developers will notice that this is "velocity").
The second very important issue is to be completely anal about your definition of "done" and about making sure that the completed tasks actually meet that definition. Your mean completion time will only be useful if you are measuring the time to completion accurately (obviously).
This effect is so powerful that I recommend "same sizing" tasks and planning everything to have a completion time of somewhere between 1 and 2 days.
There is actually one last thing you need to do. Requirements discovery never happens completely before you start development. As you write the code, you discover new things to do. It is obviously important to modify your plan to accommodate that new information. If you don't, you will end up building something that nobody needs. However, the amount of new work seems to be predictable. I made graphs of new work added to projects over a couple of years and it appears that the growth of new requirements is very similar to some of the defect discovery models (for example Littlewood). Just making a graph of new stories/tasks added over time will give you a decent idea, but I have found that a rule of thumb of adding 30% or so (over the whole project) for new requirements seems to work well.
- caseysoftware 11y agoThere's another hidden aspect: Be aware of dependencies. When you have a series of dependencies (A -> B -> C) stacked against each other, once A is late, B and C are almost guaranteed to be late. If B is late too, C suffers even more and has little chance of being on time. If you can lay out the tasks so that dependencies have slack between them so that lateness can be absorbed without shifting later tasks, you are more likely chance to hit deadlines and potentially complete the project on time. Or in more formal terms, track the Critical Path. In practical terms, I would see this all the time commuting home in DC. I walked to the train to the bus to home. If I timed it perfectly, my commute was ~25 minutes. But if I couldn't cross the street in time, I'd catch a later train which made for a later bus. Or a slightly later train would be a much later bus. When those variances stacked up, it could take an hour.
- crdoconnor 11y agoYou can also try to eliminate dependencies as well as track them. This is partly why in software it's so critical to loosely couple software. If you're working on a big old ball of mud there are so many dependencies that even the smallest task ends up taking forever. Fortunately SCRUM provides you with a block of time which you can use to decouple software independently of working on features or bugs, so this necessary work always gets done. Ha.
- crdoconnor 11y agoThere is some stuff that can easily take almost no time or can end up taking months. Two items that are commonly like this on software projects are fixing bugs (that can either turn out to be really, really hard or not bugs at all) or upgrading package dependencies (can require no changes whatsoever or can require a significant rearchitecture). I think scheduling these issues would benefit more from splitting up risk and estimated duration and estimating both separately. Perhaps by drawing a mini probability distribution for each task. Breaking down the task only helps if, in some way, analysing the constituent pieces actually helps you better estimate the risk or brings unconsidered requirements to light. Sometimes it doesn't. If you do too much of it it can also end up being a contributing factor to the delays (analysing every last detail).