90% is a best of fleet number. But for economic analysis you should really assume a lower number, unless you can guarantee that you are the cheapest producer at
by jerven 11y ago
90% is a best of fleet number. But for economic analysis you should really assume a lower number, unless you can guarantee that you are the cheapest producer at all times. As demand during the day can be near double of that in an area during the night, once your type of plant is over 50% of local supply your capacity factor is not a limit but demand side is.
4.5 billion capex is a really good number for nuclear in a competent regulatory environment. Still its double the estimated project cost when started.
Funnily enough nuclear and renewables really compete hard because of this. Extra power production is nearly nothing for both compared to opex and capex, so if you can produce you shall until returns hit 0. Both love energy storage for that reason. Nuclear is more dependable i.e. less peakers on because of supply issues. But capex for wind and solar are trending too be lower, as is time to market. Leading to less risks, which affects project planning a lot.
CSPs with inbuilt storage tend to go to lower generator capacity factors so that they can take a share of the peak shaving market, due to their relative good dispatch ability (send power to the market when wanted, instead of when you can).
Wind and solar projects tend to be online and producing quickly in time measured from first concrete poured to power send to market, certainly relative to nuclear in practice. Projects also tend to be smaller scale and in independent phases. Nuclear is added a GW at a time to the market, solar and wind in smaller 50-100mw projects.
i.e. wind&solar are project wise much more agile.
- hga 11y ago4.5 billion capex is a really good number for nuclear in a competent regulatory environment. Is France one, and does anyone know what their's is?
- jerven 11y agoFlamanville, at 10.5 billion euro for 1.6 GW is not nearly as good as watts bar 2. This has had serious delays due to quality issues detected by its regulator. As had the finish and Chinese units build to the same design. Sure these are supposed by GenIII, but are currently not competitive in any way with other power sources in economic terms. 10.5 billion buys you about the same in offshore wind e.g. 3 london array installations ( 2 billion per 600 MW * 50% capacity, compared to 10.5 billion per 1600mw * 90% capacity) = 10/(1.6*.9). Big difference is london arrays take 1 year to build instead of 10 for nuclear. That alone gives a mayor difference in real project costs.
- hga 11y agoThere's not much surprise if the first version of a new design runs over budget; I'm interested in the costs of routine, serial production once those unknowns have been worked through. What about the 59 reactors already in operation, including Flamanville 1 and 2?
- jerven 11y agoThat is really hard to determine, mostly because project costs are part of the greater EdF numbers and not broken down in details for those years. So someone with better French and access should be able to answer you there. This is true not just for nuclear but all power generation before the late 90's in europe. i.e. same difficulty to getting numbers in the UK and Germany. Once these national power companies went to the stock exchanges they started to report in more detail how much projects cost. Anyway there are also number of existing reactors that are no longer running even if in the same generation as some other ones. The, unfortunate, reality is nuclear reactors are not build in serial production. Therefore learning costs do not decrease as much as you might expect. Main reasons are distance between sites, meaning many construction workers do not work on all sites. You see at most 10 units for one design. Time between forgings for mayor means parts are not made in large series so relatively little is learned. All 4 EPR sites seem to have suffered from the same issues with concrete pouring so even there learning might not have happened. Economically nuclear is in a real bind: for regulatory reasons you want big plants (1gw+), but for economic reasons you want many small ones (about 100mw). The current 1.6GW units are in many ways to big and smaller reactors would be much better project/knowledge wise. Yet the regulatory overhead for each new unit means that the firms went towards designing larger units. Bechtel marine nuclear powerplants could actually be produced in series as they are small enough to be build off site and could be made economically viable. Yet I don't expect that Bechtel ever will. But lest assume Arreva learns how to build EPRs for 5 billion and in 5 years. Which gives you EPR done right 5 billion / (1.6 GW * .7 historic capacity factor) = 4.4 to 5 billion / (1.6 GW * .9 best capacity factor) = 3.2 London array 2 billion / (.63 GW * .50 historic capacity factor) = 6/2 Even in this very optimistic scenario, offshore wind is between 100% and 60% more expensive on construction costs. Offshore wind however, still has lower opex and a much better learning curve. i.e. if ordering a london array today costs will be less than 2 billion. (big difference in reporting is that wind projects include interconnect costs which current nuclear projects do not due to sitting next to existing plants). Wind farms, also have positive decommissioning costs (those steel towers have real economic value at end of life). Both types of projects have issues with nimbys.
- trothamel 11y agoAccording to http://www.platts.com/latest-news/electric-power/washington/us-nuclear-plants-set-capacity-factor-record-21884126 http://www.platts.com/latest-news/electric-power/washington/... , 90% seems to be an average number, not a best of fleet number.
- jerven 11y agoThat is only in the last decade, and for the US. Other countries and decades have differing numbers. Still it only holds when Nuclear is a less than 50% of production. France tends to have around 77%.
- DennisP 11y agoWhy would the percentage of production being nuclear have any effect on nuclear capacity factor?
- jerven 11y agoIf you produce it but no one buys it what was the point? In fact in reality if you do that you wil pay a lot to the grid maintainer for this. Capacity factor is % utility of your max generating power output.% utility is lower if you can't produce or no one is willing to buy so you don't produce max. If you produce min deman load with nuclear at 90% capacity. The it's all good.Once you are above that demand slack means production capacity is wastes. Currently nuclear is the last to stop producing as it's variable costs are so low. If nuclear is a larger part of your grid it will tend to have a capacity factor that is equal to the average demand.
- DennisP 11y agoAh good point. That's why I think solar + nuclear is a good idea, the nuclear plants running all the time and solar adding more during the day. It won't perfectly match demand, but it'd still be better than either tech on its own.