5 ms·
I think it's an even worse investment than that. I don't believe them that the cost of decommissioning is built in. Especially since the financiers who pay dur
by illumen 11y ago
I think it's an even worse investment than that.
I don't believe them that the cost of decommissioning is built in. Especially since the financiers who pay during construction aim to sell their equity. Also in the UK, recently had to pay 4 billion worth of tax payer funds to decommission. That puts the whole thing at a loss.
Also, wind, solar and other renewable are able to be produced with a much smaller capital cost, and are only getting cheaper. Many of the tech issues are being fixed. For example, critical steam is now possible with CSP and mass production is making the systems cheaper.
The production risks for nuclear are really high, because of the high capital costs. As demonstrated by this project stalling for over a decade.
Also, uranium costs are not fixed. Over the last 18 years have changed a number of times. The price difference has been 3x (not even adjusting for inflation).
Finally, many nuclear power plants have been closed down early to fix up (14% have been closed for more than a year). Including of course Fukushima, but also other ones around the world and in the USA. There was a report of 14 plants in the USA which will likely close early. That is around 14% of plants (so far) closing earlier than planned. (There are 99 plants in the USA).
If there is a problem because the high capital costs, it seems many of the plants get closed. 100 orders for plants in the USA were cancelled, bankrupting companies.
- hga 11y agoAlso, wind, solar and other renewable are able to be produced with a much smaller capital cost, and are only getting cheaper. Are you including the energy storage systems they require to provide either baseline or peaking power? Outside of perhaps some very special locations (i.e. cover deserts with solar cells if you can get that past the BANANAs, and that still doesn't cover nighttime to, e.g., recharge electric cars) they don't, you know, actually produce the two types of electrical production the system actually needs....
- illumen 11y agoYou can build small renewable systems with all sorts of different capital costs, and all sorts of power generation abilities. Price ranges from $100 to $9billion. Nuclear projects do not happen for less than $Xbillions (and about half bankrupt before completion). Got data? Seems that most of the renewable energy is being used ok. Smarter energy management, and using salt/aluminium/steel aluminium molten lakes allows for storage/adjustment. In many places aluminium factories use up a LOT of power. They can be used as batteries of sorts. CSP solar can hold power for over 8 hours. Wind farms over provision to allow for baseload generation. Then there is storing energy in car batteries. Biomass solutions offer different power generation abilities too. All this is being done today, and systems are continually being enhanced. The point I was making though, is that you can have power generation (including batteries) at a much smaller cost for it to be useful. For example, even installing solar on a factory roof and installing batteries can be done for way under $100,000. Working nuclear plants have to close 38 days every 17 months for refuelling and maintenance. How good are they at generating baseload then?
- fnordfnordfnord 11y agoThey aren't good at generating baseload during refuelling, obviously. Most plants have more than one reactor. Refuelling usually occurs during the spring or fall, when demand is lower, and only in one reactor unit at a time. It's not exactly a feature, but it also isn't much of a bug. http://www.eia.gov/todayinenergy/images/2013.08.27/supplyreq.png http://www.eia.gov/todayinenergy/images/2013.08.27/supplyreq... http://www.eia.gov/todayinenergy/detail.cfm?id=12711 http://www.eia.gov/todayinenergy/detail.cfm?id=12711
- AnthonyMouse 11y ago> I don't believe them that the cost of decommissioning is built in. Especially since the financiers who pay during construction aim to sell their equity. Also in the UK, recently had to pay 4 billion worth of tax payer funds to decommission. That puts the whole thing at a loss. Only if you're counting the decommissioning costs for nuclear but not for anything else. By the time a mine is exhausted it's generally a Superfund site, whether they're mining coal or neodymium. And what do you do with fifty million decommissioned solar panels? > Also, uranium costs are not fixed. The amount uranium price fluctuations contribute to operating costs is negligible.
- illumen 11y agoYes, PV solar is not so good with waste either. Yes, the costs of removing broken solar panels should go into the costs for a project too. But that has nothing to do with judging weather Nuclear plants are a terrible investment. Last I read none of the closed plants in the USA had been completely decommissioned. Which is why I think the estimates for decommissioning are wrong. But perhaps there are cheaper ways to do it in the future... I don't know. Yes, fuel cost isn't that much... apparently 0.52 ¢/kWh. But that could still impact the bottom line if costs were 3x as much. But with 70 years of uranium left, I'm not sure prices will stay at similar prices over the life time of a new reactor.
- hga 11y agoLast I read none of the closed plants in the USA had been completely decommissioned. Much, if not a lot of this has to do with the simple fact that after you mothball the plany, it's easiest and cheapest to wait a while for various radioactive isotopes to decay to less hazardous stuff. As long as you mothball it properly, and maintain that, there's no hurry.
- Retric 11y agoIf the money is set aside ahead of time and invested well then sure. If your dependent on the company that operated the plant to still be around then there just going to keep putting it off until the company fails. At which point the taxpayer is stuck with the costs.
- rwcarlsen 11y agoDecommissioning costs are generally around a few hundred million $ - not more than 10% of the capital costs generally [1]. And there are very strict regulations around it - many firms are required to have a trust or other type of fund built up during operation of the facility in advance of final shutdown and decommissioning. And as others have stated, uranium price is very small part of total nuclear energy cost. [1] http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/de...
- skrause 11y agoThe German utilities just had to set aside around 35 billion dollars to decommission just about 10 nuclear power plants: http://www.bloomberg.com/news/articles/2015-09-16/why-germany-s-nuclear-power-exit-is-causing-havoc-for-utilities http://www.bloomberg.com/news/articles/2015-09-16/why-german... With that in mind I honestly don't believe the "few hundred million $".
- PhantomGremlin 11y agoI wonder where all the money will go? See my previous comment about a decommissioned plant, elsewhere in this topic. https://news.ycombinator.com/item?id=10457453 https://news.ycombinator.com/item?id=10457453 The reactor vessel is long gone. What remains on site is spent fuel, but there's nowhere to move that to. Cost was perhaps $0.23 billion but that's an approximate figure. Still, nowhere near the $3.5 billion per plant that German utilities have set aside.